PROJECT BACKGROUND – ST. MATTHEW’S COE PRIMARY AND NURSERY ACADEMY



Project Background
CELLECTA were involved in design team meetings with the main contractor, architects and acousticians to ensure all design criterias were met (and exceeded), as well as providing the ability to factor in further savings to superstructure and floor finishes preparation.
Originally, using underfloor heating within screeds on 1st floor, but drying times were delaying program. Switched to ScreedBoard 20, routed HEXATHERM XFLOOR 300 and 8mm FIBREfon fleece to give a dry fit solution which met loading requirements and acoustic performances.
Type of Construction New school, Plymouth Project size 1,850m² Products Installed ScreedBoard 20 XFLOOR 300 – 140mm FIBREfon 8mm Fleece |