Residential Case Study
PROJECT BACKGROUND – DOYLE AVENUE PORTSMOUTH



Project Background
- Scheme comprises Demolition of existing bungalow and the construction of a 250 bedroom hotel. The eight-storey, L-shaped hotel, will feature leisure facilities on the ground floor and a restaurant on the top floor, and be a Marriot Courtyard hotel. The new hotel will include a unique, rooftop glazed restaurant, and access to the hotel be via a purpose built footbridge from the existing stadium complex.
- The mix of HiDECK 18, XFLOOR 20MM, FIBREfon 10 has created the basis of the hotel. FIBREfon shallow platform floating floor treatments are Robust Detail FFT 5 compliant, with their acoustic performance third party tested. All three treatments combine a tongue and groove timber floorboard with a high compressive strength resilient layer.
Type of Construction Steel Concrete Project size 24,000 m2 Products Installed |
Suitable for all types of steel, concrete and timber floors
Products Installed Information
Uncategorized